Question 101

As a result of an IT audit, a customer has decided to move some applications from an old legacy system to a private cloud. The current server location is remote with low bandwidth. Which of the following is the best migration strategy to use for this deployment?

Options:

A.

P2V with physical data transport

B.

P2P with remote data copy

C.

V2V with physical data transport

D.

V2P with physical data transport

E.

V2P with remote data copy

Question 102

A cloud engineer is responsible for a legacy web application that runs on an on-premises VM environment. The VM environment is approaching end of life. The engineer needs to migrate the web application to the cloud as quickly as possible because the VM environment has the following limitations:

• The VM environment has a single IOGB disk.

• The VM environment still uses 10Mbps, which leaves a 100Mbps WAN connection underutilized.

• No installation media is available.

Which of the following is the best way to migrate the web application to the cloud?

Options:

A.

Use the VM import connector to import the VM into the cloud.

B.

Use import/export to import the VM as a snapshot and attach it to a cloud instance.

C.

Use REST APIs to import an image of the VM into the cloud.

D.

Use object storage to create a backup of the VM and restore data into the cloud instance.

Question 103

A corporation is evaluating an offer from a CSP to take advantage of volume discounts on a shared platform. The finance department is concerned about cost allocation transparency, as the current structure splits projects into dedicated billing accounts. Which of the following can be used to address this concern?

Options:

A.

Implementing resource tagging

B.

Defining a cost baseline

C.

Consolidating the billing accounts

D.

Using a third-party accounting tool

Question 104

A web consultancy group currently works in an isolated development environment. The group uses this environment for the creation of the final solution, but also for showcasing it to customers, before commissioning the sites in production. Recently, customers of newly commissioned sites have reported they are not receiving the final product shown by the group, and the website is performing in unexpected ways. Which of the following additional environments should the group adopt and include in its process?

Options:

A.

Provide each web consultant a local environment on their device.

B.

Require each customer to have a blue-green environment.

C.

Leverage a staging environment that is tightly controlled for showcasing

D.

Initiate a disaster recovery environment to fail to in the event of reported issues.