Whole Life Asset Management Questions and Answers

Question 45

The size of order that minimises the total cost of acquiring and holding stock is known as...

Options:

A.

Order quantity

B.

Economic Order Quantity

C.

The correct quantity

D.

Average stock

Question 46

Which of the following is the formula for calculating the re-order level?

Options:

A.

Average usage in a lead-time / Required level of safety stock

B.

Required level of safety stock x Average usage in a lead-time.

C.

Required level of safety stock – Average usage in a lead-time

D.

Average usage in a lead-time + Required level of safety stock

Question 47

SpeedyCar GmbH is a vehicle manufacturer that is launching a new electric vehicle onto the market, replacing a previous diesel vehicle. There is a lot of equipment in the manufacturing site to be changed, some new machinery to replace older machinery, and some production equipment to decommission. The costs of decommissioning would include which of the following?

Options:

A.

Costs to upgrade electric vehicle charging facilities

B.

Decontamination and cleaning costs for site areas

C.

Sales and marketing costs of the new electric vehicle

D.

Engineering drawing fees for the new electric vehicle designs

Question 48

XYZ Ltd has been adopting MRP system for years. The system helps the company improve effi-ciency greatly and generates huge cost-savings. However, MRP system is only limited to produc-tion process management and XYZ management team would like to have better insights into re-sources required across the organisation as a whole. Which software system would help XYZ management team achieve the above objective?

Options:

A.

MRP II

B.

MPS

C.

ERP

D.

P2P