The Central Government funding programme for the redevelopment of schools has been put on hold. A Review Board will decide
which programmes to continue. This funding programme covers 20% of the Pittville project costs. It is considered very likely that
the Western Area Learning Programme will be high priority due to the forecast enhanced provision of education courses for 16-18
year olds.
Should the funding profile in the Economic Case be updated?
There is a need to meet regulations that address the needs of those with Learning Difficulties and Disabilities
Should this item be recorded as a dependency within the Strategic Outline Case?
Using the Scenario, answer the following questions about scoping the proposal and preparing the Strategic Outline Case for
the Pittville project.
Decide whether the approach is appropriate for stage 1, and select the response that supports your decision.
There is a risk that the local planning authority may reject proposals for development of the Old Fire Station Headquarters site. This
will cause delays to the project.
Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?
Using the Scenario and the extract below from the Revenue Budget for the Pittville project, answer the following
questions. (Note. The figures entered are correct).
Which 2 observations correctly evaluate the Expenditure?