New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

All C_TS422_2022 Test Inside SAP Questions

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 13

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.

Question 14

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Product type

B.

Selection screen for views

C.

Selection screen for plants

D.

Base unit of measure

Question 15

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Question 16

Which standard item categories can you select inside a bill of material (BOM)?

Note: There are 2 correct answers to this question

Options:

A.

Work item

B.

Variable-size item

C.

Non-stock item

D.

WBS item