Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Agile Analysis IIBA-AAC IIBA Study Notes

Page: 3 / 3
Total 85 questions

IIBA Agile Analysis Certification Questions and Answers

Question 9

A practice common to most agile approaches is to require that the items in the product backlog that are targeted to be delivered next, are:

Options:

A.

Loosely prioritized with some having the same priority

B.

Strictly prioritized, and sequenced from smallest to largest work effort

C.

Unprioritized, but with known business value

D.

Strictly prioritized and forced ranked

Question 10

The delivery team is reviewing information that starts with a broad view of the solution components and drills down to a level of granularity, including acceptance criteria, that supports solution build activities. The team is using the following technique:

Options:

A.

Story elaboration

B.

Real options

C.

Detailed story

D.

Backlog management

Question 11

In the past, a team has been unable to deliver solutions in a timely manner and they feel this is due to the customer being unable to decide what they want. The team has decided to ask the customer to “sign-off” on their requirements. This violates the following value statement:

Options:

A.

Individuals and interactions over process and tools

B.

Prioritizing outputs over outcomes

C.

Working solutions over comprehensive documentation

D.

Customer collaboration over contract negotiation

Question 12

A team demonstrating the following characteristics:

Expects rapid change

Incorporates learning & feedback

Has a preference for shorter time frames

Treats plans as testable hypothesis

is following planning practices that are described as:

Options:

A.

Predictive and adaptive

B.

Adaptive and hypothesis

C.

Iterative and predictive

D.

Iterative and adaptive

Page: 3 / 3
Total 85 questions