BCS Related Exams
TA12 Exam
A company wants to develop a web site to implement an on-line sales channel. The company has decided to do some usability testing, but resources are limited. The usability testing has therefore to be done as efficient as possible. Which THREE techniques would you recommend?
[K4] 3 credits, 2 out of 3 correct 1 credit
As a test analyst you are involved in the early stages of an acceptance test for a Product Data Management system. You are asked to write test designs and test cases based on use cases. An early version of the system is also already available. It is a known fact that on the implementation level many things will change (including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation.
What is the BEST option regarding the level of detail and documentation required for test cases in the project?
[K4] 3 credits
In an organization using keyword-driven automation, which of the following activities typically is the responsibility of the test analyst?
[K2] 1 credit