iSQI Related Exams
CTFL_UK Exam

Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
What is the Risk Priority Number for risk item number 2? 2 credits