New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Note: This exam is available on Demand only. You can Pre-Order this Exam and we will arrange this for you.

Pre-Order Your Associate in Project Management (APM) APM-001

You can pre-order your Associate in Project Management (APM) exam to us and we will make it available in 2 Weeks to 3 Weeks maximum. CertsTopics.com Team will Arrange All Real Exam Questions only from Real Exam within next 2 Weeks to 3 Weeks Time only and make them available for you.

How to Place Pre-Order You Exams:

  1. Click to "Add to Cart"
  2. Our Expert will arrange real Exam Questions within 2 Weeks to 3 Weeks especially for you.
  3. You will be notified within (2 Weeks to 3 Weeks time) once your Exam is ready with all Real Questions with PDF + Testing Engine format.

Why to Choose CertsTopics?

  • Only we can provide you this Pre-Order Exam service. If your required exam is not available on our website, Our Team will get it ready for you on the cost price!
  • Over 5000+ our customers worldwide are using this pre-ordering service.
  • Approx 99.8% pass rate among our customers - at their first attempt!
  • 90 days of free updates included!

In the unlikely event if we can't make this exam available to you then you will issue a full refund! So there is no risk involve at all.

READY TO MAKE YOUR "APM-001" PRE-ORDER?

Yes, I agree

$850  $425

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Associate in Project Management (APM) Questions and Answers

Question 1

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Buy Now
Question 2

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

Options:

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Question 3

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G