Pre-Order Your Associate in Project Management (APM) APM-001

You can pre-order your Associate in Project Management (APM) exam to us and we will make it available in 2 Weeks to 3 Weeks maximum. CertsTopics.com Team will Arrange All Real Exam Questions only from Real Exam within next 2 Weeks to 3 Weeks Time only and make them available for you.

How to Place Pre-Order You Exams:

  1. Click to "Add to Cart"
  2. Our Expert will arrange real Exam Questions within 2 Weeks to 3 Weeks especially for you.
  3. You will be notified within (2 Weeks to 3 Weeks time) once your Exam is ready with all Real Questions with PDF + Testing Engine format.

Why to Choose CertsTopics?

  • Only we can provide you this Pre-Order Exam service. If your required exam is not available on our website, Our Team will get it ready for you on the cost price!
  • Over 5000+ our customers worldwide are using this pre-ordering service.
  • Approx 99.8% pass rate among our customers - at their first attempt!
  • 90 days of free updates included!

In the unlikely event if we can't make this exam available to you then you will issue a full refund! So there is no risk involve at all.

READY TO MAKE YOUR "APM-001" PRE-ORDER?

Yes, I agree

$850  $425

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Associate in Project Management (APM) Questions and Answers

Question 1

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Buy Now
Question 2

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Question 3

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)