Question 1

Which phase transfers a successfully deployed new service to the Operate phase?

Options:

A.

Build

B.

Deliver

C.

Deploy

D.

Plan

Buy Now
Question 2

What is the correct order for the five SMFs found in the Deliver Phase?

Options:

A.

Project Planning, Envision, Build, Deploy, Stabilize

B.

Envision, Project Planning, Build, Stabilize, Deploy

C.

Envision, Build, Project Planning, Deploy, Stabilize

D.

Envision, Project Planning, Stabilize, Build, Deploy

Question 3

What is the focus of the GRC SMF in the Operate phase?

Options:

A.

Documentation and Recording

B.

IT environment and configuration

C.

Management Reviews

D.

Policy retirement

Question 4

The service desk is a component of which SMF?

Options:

A.

Business/IT alignment SMF

B.

Customer Service SMF

C.

Policy SMF

D.

Service Monitoring and Control SMF

Question 5

Which SMF has a goal to take remedial actions that minimize the impact of service incidents and system events?

Options:

A.

Customer Service

B.

Incident Management

C.

Service Desk

D.

Service Monitoring and Control

Question 6

Why would you use the GRC SMF?

Options:

A.

to assess, monitor and control risk

B.

to maintain configuration baselines

C.

to manage change

D.

to understand accountabilities

Question 7

Does the Team SMF ensure that someone is ultimately accountable for the work required in the Plan Phase?

Options:

A.

Yes

B.

No

Question 8

Is the Portfolio Management Review focused on understanding the state of supply and demand for IT services and directing investments to make sure that the business value of IT is realized?

Options:

A.

Yes

B.

No

Question 9

Performing IT accounting is part of which SMF?

Options:

A.

Business/IT Alignment SMF

B.

Financial Management SMF

C.

Policy Management SMF

D.

Reliability Management SMF

Question 10

Which Team role type is the accountable role type for the Deliver Phase?

Options:

A.

Program manager

B.

Product manager

C.

Test manager

D.

Solution manager