Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free and Premium Exin CDCS Dumps Questions Answers

Page: 1 / 5
Total 60 questions

EXIN EPI Certified Data Centre Specialist Questions and Answers

Question 1

What is the calculation for the desired attenuation factor for shielding material?

Options:

A.

A = 20 log (M / R)

Where

A is Attenuation

M is the maximum acceptable value

R is the real value measured

B.

A = M / R

Where

C.

A is Attenuation

M is the maximum acceptable value

R is the real value measured

D.

A = 20 log (R / M)

Where

A is Attenuation

R is the real value measured

M is the maximum acceptable value

E.

You do not have to calculate the attenuation factor for shielding material as it always has the same attenuation

Buy Now
Question 2

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

Options:

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Question 3

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

Options:

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Question 4

You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 °C / 20 °F. Calculate the approximate CFM required to cool the equipment in the rack.

Options:

A.

Approximately 1,500 CFM

B.

Approximately 1,000 CFM

C.

Approximately 500 CFM

D.

Approximately 160 CFM

Question 5

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

Options:

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Question 6

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

Options:

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Question 7

What is the main disadvantage of using a ToR (Top of Rack) design?

Options:

A.

A single ToR (Top of Rack) switch is more expensive than an EoR (End of Row) switch.

B.

You need a separate rack to install all your ToR (Top of Rack) switches.

C.

There will be more switches to manage.

D.

A ToR (Top of Rack) switch has only optical interfaces.

Question 8

Which formula is correct?

Options:

A.

Phase-to-Neutral Voltage = Phase-to-Phase voltage * 1.732

B.

Phase-to-Neutral Voltage = Phase-to-Phase voltage /1.732

C.

Phase-to-Neutral Voltage = Phase-to-Neutral voltage * 1.732

D.

Phase-to-Neutral Voltage = (Phase-to-Phase voltage * 1.732) / Phase-to-Neutral Voltage

Question 9

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

Options:

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Question 10

What should be considered when installing overhead data cabling?

Options:

A.

To maintain minimum separation from power and ensure that the fire detection and suppression systems are not hindered.

B.

Copper data cabling should not be placed in metal cable trays.

C.

Optical fiber cabling should always be positioned on top of the copper cabling in the same cable tray to avoid damage to the sensitive optical fiber.

D.

All cabling should make sharp bends directly into the rack to avoid usage of additional space and blocking the airflow on top of the rack.

Question 11

You are allowed to use a calculator for this question.

A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.

The temperature is 20 °C / 68 °F.

The required design concentration is 7%.

The S-Factor is 0.1359 (metric) / 1.885 (imperial).

Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

Options:

A.

Approximately 410 kg / 900 lbs

B.

Approximately 820 kg / 1,800 lbs

C.

Approximately 1,390 kg / 3,000 lbs

D.

Approximately 1,640 kg / 3,600 lbs

Question 12

From the options indicated, what is the correct starting point for the raised floor installation?

Options:

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Question 13

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch H₂O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

Options:

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Question 14

What indicates the breaking capacity of a fuse or breaker?

Options:

A.

Mechanical strength of the casing of a fuse or breaker.

B.

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.

The current at which the device will trip.

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Question 15

The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.

What would be the best option?

Options:

A.

Do not use fire-rated glass due to the size limit and replace it with normal glass.

B.

Split the window in two equal parts using an aluminum frame.

C.

Split the window into parts smaller than specified as the maximum exposed area and ensure fire-rated frames are used.

D.

Split the window in two equal parts fitted together with transparent silicon glue.

Question 16

A data center has its own power supply from the public utility and receives chilled water supply from the building owner.

What needs to be taken into consideration when calculating the PUE?

Options:

A.

Nothing, as the chiller plant in the building also uses electrical power

B.

You will need to take the value for COP of the chiller plant into consideration

C.

You will need to take a weight factor of 0.4 for district chilled water into consideration

D.

PUE calculations are not possible in shared buildings

Question 17

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

Options:

A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

Question 18

What should you consider when using raised floor tiles with air deflectors or louvers?

Options:

A.

Tiles with air deflectors or louvers can be very heavy.

B.

Tiles with air deflectors or louvers will reduce the cooling capacity of the tile.

C.

Tiles with air deflectors or louvers do not allow for a flexible cooling solution.

D.

Tiles with air deflectors or louvers can only be used to cool storage equipment.

Page: 1 / 5
Total 60 questions