Question 9

A sprinkler system employs automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately when a head opens. What is this called?

Options:

A.

Dry pipe system

B.

Deluge system

C.

Pre-action system

D.

Wet pipe system

Question 10

The electrical diagram of the data center shows the following UPS configuration and has a load of 80 kW.

What is the set-up in this data center?

Options:

A.

2+N+1

B.

2(N+1)

C.

N+N(+1)

D.

(N+1)-(N+1)

Question 11

You are installing new copper cabling.

What is the advantage or disadvantage of choosing pre-terminated category 6 or 6A cabling?

Options:

A.

Pre-terminated cabling is already factory tested and saves installation time.

B.

There is no advantage as most new copper cabling network designs are based on category 3 or 5E for horizontal cabling.

C.

Pre-terminated cabling has a higher fire rating.

D.

Pre-terminated cabling makes ordering of the copper cables more complex, as you need to know in advance on which side the male or female connector needs to be located.

Question 12

Maximum exposed area of fire-rated glass is 2 m², but the window is 5 m². What is the best option?

Options:

A.

Replace with normal glass

B.

Split into two equal parts with silicone

C.

Split into two equal parts with aluminum frame

D.

Split into smaller parts within 2 m² using fire-rated frames