Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

ECCouncil 512-50 Exam With Confidence Using Practice Dumps

Exam Code:
512-50
Exam Name:
EC-Council Information Security Manager (E|ISM)
Certification:
Vendor:
Questions:
404
Last Updated:
Feb 22, 2025
Exam Status:
Stable
ECCouncil 512-50

512-50: EISM Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the ECCouncil 512-50 (EC-Council Information Security Manager (E|ISM)) exam? Download the most recent ECCouncil 512-50 braindumps with answers that are 100% real. After downloading the ECCouncil 512-50 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the ECCouncil 512-50 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the ECCouncil 512-50 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (EC-Council Information Security Manager (E|ISM)) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA 512-50 test is available at CertsTopics. Before purchasing it, you can also see the ECCouncil 512-50 practice exam demo.

EC-Council Information Security Manager (E|ISM) Questions and Answers

Question 1

Which of the following functions implements and oversees the use of controls to reduce risk when creating an information security program?

Options:

A.

Risk Assessment

B.

Incident Response

C.

Risk Management

D.

Network Security administration

Buy Now
Question 2

A Security Operations Centre (SOC) manager is informed that a database containing highly sensitive corporate strategy information is under attack. Information has been stolen and the database server was disconnected. Who must be informed of this incident?

Options:

A.

Internal audit

B.

The data owner

C.

All executive staff

D.

Government regulators

Question 3

The risk found after a control has been fully implemented is called:

Options:

A.

Residual Risk

B.

Total Risk

C.

Post implementation risk

D.

Transferred risk