Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium CompTIA PK0-005 Dumps Questions Answers

Page: 1 / 34
Total 447 questions

CompTIA Project+ Certification (2026) Questions and Answers

Question 1

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

Options:

A.

Too much time might be spent generating project delays.

B.

The project manager might be seen as weak.

C.

The number of change requests throughout the project might be reduced.

D.

Some stakeholders might not be completely satisfied.

Buy Now
Question 2

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Question 3

Which of the following is a disadvantage of a cloud model?

Options:

A.

Limited processing and storage capacity

B.

Limited expansion capability

C.

Longer latency time

D.

Higher dependency on the vendor

Question 4

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Question 5

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

Options:

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Question 6

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

Options:

A.

Pareto

B.

Run

C.

Control

D.

Histogram

Question 7

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

Options:

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Question 8

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Question 9

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?

Options:

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Question 10

Which of the following best describes the results?

Options:

A.

No correlation exists between the extra hours worked and the number of defects in the code.

B.

A positive correlation exists between the extra hours worked and the number of defects in the code.

C.

A non-linear correlation exists between the extra hours worked and the number of defects in the code.

D.

A negative correlation exists between the extra hours worked and the number of defects in the code.

Question 11

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Question 12

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Question 13

A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?

Options:

A.

Meeting minutes

B.

Action items

C.

Timeboxing

D.

Follow-up notes

Question 14

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

Options:

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Question 15

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Question 16

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question 17

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Question 18

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options:

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Question 19

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Question 20

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options:

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Question 21

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Question 22

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

Options:

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Question 23

An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?

Options:

A.

System downtime

B.

Risk assessment

C.

Cost

D.

Customer experience

Question 24

Which of the following statements best describes a content management system?

Options:

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Question 25

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Question 26

As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?

Options:

A.

Subscription

B.

Subcontract

C.

Lease

D.

Build

Question 27

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Question 28

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Question 29

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Question 30

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

Options:

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Question 31

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

Options:

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Question 32

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Question 33

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Question 34

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Options:

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Question 35

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

Options:

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Question 36

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Question 37

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

Options:

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Question 38

Which of the following best describes a rollback plan?

Options:

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Question 39

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Question 40

A project's QA team needs to validate functionality in a timely and cost-effective way to ensure good coverage every time a new change is integrated. Which of the following test should the team execute?

Options:

A.

Sanity

B.

Manual

C.

Automated

D.

Regression

Question 41

A project team that handles sensitive data analysis recently onboarded three new employees. Which of the following should the PM do first?

Options:

A.

Check employee security clearance

B.

Allow access to the internet on corporate computers

C.

Train the new employees to handle sensitive data

D.

Execute an analysis of the sensitive data

Question 42

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Question 43

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Question 44

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Question 45

Which of the following project types is best managed as a waterfall project?

Options:

A.

Data analytics

B.

Research

C.

Software development

D.

Real property

Question 46

A PM is reviewing objectives for a project in a new industry. Which of the following items should the PM review first?

Options:

A.

Applicable regulations and standards

B.

Relevance to the global environment

C.

Company vision, mission, and values

D.

Impact to the corporate brand

Question 47

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Question 48

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

Options:

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

Question 49

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

Options:

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Question 50

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Question 51

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Question 52

Given the following information:

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Question 53

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Question 54

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Options:

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Question 55

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options:

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

Question 56

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

Options:

A.

Rollback plan

B.

Release plan

C.

Deployment plan

D.

Contingency plan

Question 57

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

Options:

A.

Performance

B.

Smoke

C.

Regression

D.

Unit

Question 58

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Question 59

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

Options:

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Question 60

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?

Options:

A.

Evaluate the project's communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Question 61

A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

Options:

A.

The vendor's proposed schedule does not align with the desired schedule.

B.

The vendor is new and not well established in the market.

C.

The vendor has been linked to ESG concerns within the past month

D.

The vendor's quote was the highest of all the proposals.

Question 62

A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?

Options:

A.

Risk register

B.

Detailed scope statement

C.

Requirements Traceability Matrix

D.

Task board

Question 63

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Question 64

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

Options:

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Question 65

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Options:

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Question 66

During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?

Options:

A.

In-person meetings

B.

Email

C.

Telephone

D.

Videoconference

Question 67

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

Options:

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Question 68

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Question 69

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

Options:

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Question 70

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Question 71

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

Options:

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Question 72

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Question 73

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Question 74

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

Options:

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Question 75

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

Options:

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Question 76

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Question 77

Which of the following best describes the reason a waterfall approach would be used for a project?

Options:

A.

The executive team still has no clear requirements for the product.

B.

The executive team is looking to review the product only once after the product is finalized.

C.

The executive team is expecting constant delivery of components.

D.

The executive team wants to reduce the budget for development.

Question 78

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

Options:

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

Question 79

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Options:

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Question 80

A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?

Options:

A.

Inform all stakeholders.

B.

Update the issue register.

C.

Follow the escalation path.

D.

Initiate a change request.

Question 81

Which of the following best describes a program in the context of project management?

Options:

A.

It is a group of unrelated projects within an organization

B.

It is used to represent the daily activities of multiple projects

C.

It is a consolidation of related projects with a common goal

D.

It provides the definition of a project workload

Question 82

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Question 83

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options:

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Question 84

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Question 85

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Question 86

A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?

Options:

A.

Milestone chart

B.

Task board

C.

Work breakdown structure

D.

Detailed project plan

Question 87

A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?

Options:

A.

Credit cards

B.

Mission statements

C.

Site certificates

D.

Trademarks

Question 88

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Question 89

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?

Options:

A.

Issue log

B.

Risk register

C.

Change log

D.

Defect log

Question 90

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Question 91

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Question 92

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Question 93

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

Options:

A.

Create a list of tasks and share it with the team.

B.

Resend the scope of work to the team.

C.

Review the Gantt chart weekly with the team.

D.

Have the project sponsor meet with the team.

Question 94

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

Options:

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

Question 95

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

Options:

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Question 96

Which of the following aspects are true of waterfall as compared to agile? (Select two).

Options:

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Question 97

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Question 98

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Question 99

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Options:

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Question 100

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

Options:

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Question 101

A project manager would like to add external engineers to the current team. Engineers will participate in specific tasks only during the testing phase. Which of the following contracts would the project manager most likely use in this situation?

Options:

A.

Time and material

B.

Fixed-price

C.

Warranty

D.

Cost-plus

Question 102

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Question 103

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Question 104

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

Options:

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Question 105

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Question 106

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Question 107

Which of the following situations would require a project manager to revise the communication plan during a project's execution?

Options:

A.

A change is approved that impacts the project schedule and budget

B.

The test results are not as expected

C.

The team is unclear which meetings they should attend

D.

A stakeholder requests some changes to the scope

Question 108

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Question 109

During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?

Options:

A.

Assign tasks and responsibilities to the team members

B.

Provide an overview of the project objectives and timeline

C.

Develop a project communication plan

D.

Set a meeting cadence for the rest of the project

Question 110

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

Options:

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Question 111

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Question 112

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Options:

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Question 113

Which of the following pieces of data are examples of Pll?

Options:

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Question 114

Which of the following statements best describes Kanban?

Options:

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Question 115

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Question 116

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Question 117

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Question 118

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Question 119

Which of the following would a scrum team discuss during a daily stand-up meeting?

Options:

A.

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Question 120

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

Options:

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Question 121

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Question 122

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

Options:

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Question 123

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

Options:

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Question 124

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Question 125

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Question 126

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options:

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Question 127

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Question 128

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

Options:

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Question 129

During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?

Options:

A.

Preliminary scope statement

B.

Procurement needs assessment

C.

Project success criteria

D.

Work breakdown structure

Question 130

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

Options:

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Question 131

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Question 132

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Question 133

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Question 134

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Page: 1 / 34
Total 447 questions