Weekend Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CompTIA PK0-005 Dumps

Page: 1 / 18
Total 239 questions

CompTIA Project+ Certification (2024) Questions and Answers

Question 1

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

Options:

A.

A risk budget

B.

A risk impact

C.

A change request

D.

A contingency plan

Question 2

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Question 3

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Question 4

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Part 2:

Options:

Question 5

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

Options:

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Question 6

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Question 7

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

Options:

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Question 8

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Question 9

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

Options:

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Question 10

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Question 11

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

Options:

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Question 12

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Options:

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Question 13

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Question 14

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.

The project meets the expected milestones and finishes on time and within budget.

Question 15

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Question 16

Which of the following tools is best to use for storing lessons learned?

Options:

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Question 17

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

Options:

A.

SOW

B.

RFI

C.

RFQ

D.

WBS

Question 18

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

Options:

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

Question 19

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Question 20

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Question 21

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Question 22

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Question 23

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Question 24

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Options:

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Question 25

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Question 26

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Options:

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Question 27

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Question 28

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Question 29

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Question 30

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Question 31

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Question 32

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

Question 33

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Question 34

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Question 35

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Question 36

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

Options:

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Question 37

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Question 38

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Question 39

Which of the following would be considered operational security?

Options:

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Question 40

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question 41

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

Options:

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Question 42

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Question 43

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options:

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Question 44

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Options:

A.

Implement the change.

B.

Approve the test plan.

C.

Notify customers.

D.

Develop a rollback plan.

Question 45

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Options:

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Question 46

A team member identifies a critical issue in production. Which of the following should the project manager apply?

Options:

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Question 47

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Question 48

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Question 49

Which of the following contract types in project procurement has the highest risk for the buyer?

Options:

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Question 50

Which of the following tools is best to use when conducting project meetings across time zones?

Options:

A.

Text

B.

Calendaring tools

C.

Videoconference

D.

Email

Question 51

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

Options:

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

Question 52

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Options:

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Question 53

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Question 54

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Options:

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Question 55

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Options:

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Question 56

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Question 57

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

Options:

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Question 58

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Question 59

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Question 60

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

Options:

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Question 61

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

Options:

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Question 62

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Options:

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Question 63

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

Options:

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Question 64

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

Options:

A.

The project closeout report

B.

A handover to operations

C.

Phase-gate review documentation

D.

A transition plan

Question 65

Which of the following software programs would be BEST to use lo store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question 66

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question 67

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Options:

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Question 68

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Options:

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Question 69

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Question 70

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Question 71

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Page: 1 / 18
Total 239 questions