CIPS L4M3

L4M3: CIPS Level 4 Diploma in Procurement and Supply Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the CIPS L4M3 (Commercial Contracting) exam? Download the most recent CIPS L4M3 braindumps with answers that are 100% real. After downloading the CIPS L4M3 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the CIPS L4M3 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the CIPS L4M3 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Commercial Contracting) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA L4M3 test is available at CertsTopics. Before purchasing it, you can also see the CIPS L4M3 practice exam demo.

Commercial Contracting Questions and Answers

Question 1

Since services are intangible, so KPIs for services must be qualitative in all circumstances. Is this statement correct?

Options:

A.

No, KPIs for services must always be quantitative so that they can be measured easily

B.

No, some KPIs for services are measurable by means of outcome, time and space performed

C.

Yes, quantitative KPIs are limited to timeliness of supply of goods, defective rates and in-full quantities, which are applied to monitor supplier of physical goods

D.

Yes, the only measure mattered to supply of services is end-users' satisfaction

Buy Now
Question 2

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?

1. Warranties

2. Force majeure clauses

3. Penalty clauses

4. Service credits

Options:

A.

1 and 3 only

B.

3 and 4 only

C.

1 and 2 only

D.

4 and 2 only

Question 3

Streaming Ltd is a music streaming provider based in the UK. The company is looking for extending its presence in the US. To achieve this, the company needs to outsource the data centre service to a local company. To monitor the performance, the procurement manager would like to introduce a service level agreement (SLA) to the data centre service provider. Which of the following should be included in the SLA?

1. System availability

2. The mean time to recover from system failure

3. The actual number of on-time service delivery

4. Dispute resolution procedure

Options:

A.

1, 3 and 4 only

B.

1, 2 and 4 only

C.

1, 2 and 3 only

D.

2, 3 and 4 only