New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Note! The RE18 Exam is no longer valid. To find out more, please contact us through our Live Chat or email us.

BCS RE18 Exam With Confidence Using Practice Dumps

Exam Code:
RE18
Exam Name:
BCS Practitioner Certificate in Requirements Engineering 2018
Certification:
Vendor:
Questions:
40
Last Updated:
Jan 15, 2025
Exam Status:
Stable
BCS RE18

RE18: BCS Other Certification Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the BCS RE18 (BCS Practitioner Certificate in Requirements Engineering 2018) exam? Download the most recent BCS RE18 braindumps with answers that are 100% real. After downloading the BCS RE18 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the BCS RE18 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the BCS RE18 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (BCS Practitioner Certificate in Requirements Engineering 2018) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA RE18 test is available at CertsTopics. Before purchasing it, you can also see the BCS RE18 practice exam demo.

BCS Practitioner Certificate in Requirements Engineering 2018 Questions and Answers

Question 1

A business analyst has collected the following legal requirement in support of a project seeking to improve the services provided by a children's charity:

The system must record all the details of the children and young people we interact with.

The project is in the early phases of requirements elicitation. At this stage, the business analyst is trying to ensure that they have captured the broad requirements.

Which style of requirements document is the business analyst constructing, and what additional (essential) attribute will they need to record?

Options:

A.

Requirements catalogue; owner

B.

Requirements catalogue; requirement ID

C.

Requirements list; business area

D.

Requirements list; source

Buy Now
Question 2

A set of requirements for a new online health information portal have been prioritized using

MoSCoW:

REQ#1: (S)

REQ#2: (C)

REQ#3: (S)

REQ#4: (M)

REQ#5: (M)

REQ#6: (C)

REQ#7: (W)

Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.

Which two requirements will now be added to the first iteration build?

Options:

A.

REQ#1 and REQ#3

B.

REQ#2 and REQ#6

C.

REQ#4 and REQ#5

D.

REQ#6 and REQ#7

Question 3

A project sponsor has been asked to validate requirements in the requirements validation stage of the requirements engineering framework.

The primary validation role of the project sponsor is to ensure that the requirements are what at this dstage?

Options:

A.

Aligned with business objectives

B.

Compliant with quality standards and policies

C.

Technically feasible

D.

Unambiguous