An international travel operator has a customer services department responsible for investigating complaints made by holidaymakers. The department has five members of staff based in its head office.
A business analyst is working on a project to replace the existing holiday management system and has compiled the following requirements from a range of elicitation activities:
1. The solution should be fully accessible in the English, French and German languages.
2. Users should be able to retrieve holiday details by booking reference number.
3. Holiday providers shall be able to add the details, date and prices of their tours directly onto the system.
4 The solution will be able to support up to 2000 concurrent active users.
5. The solution will be restorable from back-up within 4 hours.
6. The solution should be able to retrieve holiday details within 10 seconds
Which of the following represents the correct categorization of the requirements?
A project sponsor has been asked to validate requirements in the requirements validation stage of the requirements engineering framework.
The primary validation role of the project sponsor is to ensure that the requirements are what at this dstage?
A set of requirements for a new online health information portal have been prioritized using
MoSCoW:
REQ#1: (S)
REQ#2: (C)
REQ#3: (S)
REQ#4: (M)
REQ#5: (M)
REQ#6: (C)
REQ#7: (W)
Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.
Which two requirements will now be added to the first iteration build?
A business analyst is in the process of validating a set of requirements produced for a new business initiative and the following needs agreement:
That the requirements...
1) Are within the scope of the project.
2) Can be verified when they have been implemented.
3) Express business needs clearly and correctly.
Who is responsible for this agreement?
A business analyst has collected the following legal requirement in support of a project seeking to improve the services provided by a children's charity:
The system must record all the details of the children and young people we interact with.
The project is in the early phases of requirements elicitation. At this stage, the business analyst is trying to ensure that they have captured the broad requirements.
Which style of requirements document is the business analyst constructing, and what additional (essential) attribute will they need to record?
Below are statements about what a use case model can help the analyst to do:
A) Establish the scope of a project.
B) Identify functional requirements.
C) Understand how data sets are related to each other.
D) Define the business rules in a process.
E) Validate how complete a requirements set is.
Which of these statements are true?