New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

AACE International PSP Exam With Confidence Using Practice Dumps

Exam Code:
PSP
Exam Name:
Planning & Scheduling Professional (PSP) Exam
Certification:
Questions:
163
Last Updated:
Dec 27, 2024
Exam Status:
Stable
AACE International PSP

PSP: Professional Level Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the AACE International PSP (Planning & Scheduling Professional (PSP) Exam) exam? Download the most recent AACE International PSP braindumps with answers that are 100% real. After downloading the AACE International PSP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the AACE International PSP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the AACE International PSP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Planning & Scheduling Professional (PSP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PSP test is available at CertsTopics. Before purchasing it, you can also see the AACE International PSP practice exam demo.

Related AACE International Exams

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 1

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Buy Now
Question 2

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Question 3

Which of the following statements is true?

Options:

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor

B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor

C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner

D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor