Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

SAP C_TS422_2023 Exam With Confidence Using Practice Dumps

Exam Code:
C_TS422_2023
Exam Name:
SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Vendor:
Questions:
80
Last Updated:
Apr 26, 2025
Exam Status:
Stable
SAP C_TS422_2023

C_TS422_2023: SAP Certified Application Specialist Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the SAP C_TS422_2023 (SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing) exam? Download the most recent SAP C_TS422_2023 braindumps with answers that are 100% real. After downloading the SAP C_TS422_2023 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the SAP C_TS422_2023 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the SAP C_TS422_2023 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA C_TS422_2023 test is available at CertsTopics. Before purchasing it, you can also see the SAP C_TS422_2023 practice exam demo.

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.

Options:

A.

Opening period

B.

Total replenishment lead time

C.

Float after production

D.

Setup time

Buy Now
Question 2

What are the key features of using a low-level code? Note: There are 2 correct answers to this question.

Options:

A.

To determine the priority of alternative components inside ATP

B.

To determine how costs are rolled up by product costing

C.

To determine the sequence in which materials are planned in MRP

D.

To determine the use of sub-items inside material BOM (bill of material)

Question 3

Which time elements does MRP consider in backward scheduling to determine the basic dates for components from dependent requirements? Note: There are 2 correct answers to this question.

Options:

A.

Planned delivery time

B.

Total replenishment lead time

C.

Operation duration

D.

In-house production time