SAP C_TS412_2021

C_TS412_2021: SAP Certified Application Associate Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the SAP C_TS412_2021 (SAP Certified Application Associate - SAP S/4HANA Project Systems) exam? Download the most recent SAP C_TS412_2021 braindumps with answers that are 100% real. After downloading the SAP C_TS412_2021 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the SAP C_TS412_2021 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the SAP C_TS412_2021 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (SAP Certified Application Associate - SAP S/4HANA Project Systems) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA C_TS412_2021 test is available at CertsTopics. Before purchasing it, you can also see the SAP C_TS412_2021 practice exam demo.

SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Question 1

Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

Options:

A.

Structure overview for budgets

B.

Hierarchical report on budget updates

C.

Cost element report on budget updates

D.

Line item report for budgets

Buy Now
Question 2

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

Options:

A.

Assign a purchase order for external processing to the project definition.

B.

Create an external activity in a network.

C.

Create a service milestone.

D.

Create a service activity in a network.

Question 3

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

Options:

A.

Use an offset of two days for the relationship of both activities.

B.

Use an offset of two days for milestone date.

C.

Use an offset of two days for the requirement date of the material component

D.

Calculate the start date of the activity and set the constraint "Must start on" accordingly.