New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CIPS L4M3 Exam With Confidence Using Practice Dumps

Exam Code:
L4M3
Exam Name:
Commercial Contracting
Vendor:
Questions:
190
Last Updated:
Dec 22, 2024
Exam Status:
Stable
CIPS L4M3

L4M3: CIPS Level 4 Diploma in Procurement and Supply Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the CIPS L4M3 (Commercial Contracting) exam? Download the most recent CIPS L4M3 braindumps with answers that are 100% real. After downloading the CIPS L4M3 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the CIPS L4M3 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the CIPS L4M3 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Commercial Contracting) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA L4M3 test is available at CertsTopics. Before purchasing it, you can also see the CIPS L4M3 practice exam demo.

Commercial Contracting Questions and Answers

Question 1

Which of the following are reasons why a buying organisation adopts a model contract?

1. Extremely advantageous terms for buyer

2. Correct legal terminology

3. Supplier cannot make variation to the model form

4. Specific to industry

Options:

A.

1 and 2 only

B.

2 and 4 only

C.

2 and 3 only

D.

1 and 4 only

Buy Now
Question 2

Which of the following may be a benefit for purchaser in using call off contract?

Options:

A.

Ability to discover new potential suppliers

B.

No long-term commitment required

C.

Secured supply

D.

Maintaining a degree of competition between suppliers

Question 3

In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?

Options:

A.

No, the supplier delivers within a reasonable time

B.

Yes, late delivery is a force majeure event

C.

Yes, the supplier has breached the contract

D.

No, supplier has shortened lead time to 1 day