Month End Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

BCS TAE Exam With Confidence Using Practice Dumps

Exam Code:
TAE
Exam Name:
ISTQB Certified Tester Advanced Level-Test Automation Engineering
Vendor:
Questions:
40
Last Updated:
Jan 24, 2025
Exam Status:
Stable
BCS TAE

TAE: Test Automation Engineering Exam 2024 Study Guide Pdf and Test Engine

Are you worried about passing the BCS TAE (ISTQB Certified Tester Advanced Level-Test Automation Engineering) exam? Download the most recent BCS TAE braindumps with answers that are 100% real. After downloading the BCS TAE exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the BCS TAE exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the BCS TAE exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (ISTQB Certified Tester Advanced Level-Test Automation Engineering) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA TAE test is available at CertsTopics. Before purchasing it, you can also see the BCS TAE practice exam demo.

ISTQB Certified Tester Advanced Level-Test Automation Engineering Questions and Answers

Question 1

You are reviewing the testability of your SUT.

Which of the following BEST refers to the characteristic of OBSERVABILITY?

Options:

A.

The ability of the SUTto perform its intended function for a specified period of time

B.

The ability to exercise the SUT by entering inputs, triggering events and invoking methods

C.

The ability of the SUT to prevent unauthorized access to its components or data.

D.

The abilityto identify states, outputs, intermediate result and error messages in the SUT

Buy Now
Question 2

A regression test suite consist of 500 test cases which are allexecuted manually. The business case for a pilot project is based on the adoption of test automation using a commercial tool that will reduce the execution time by a factor of 90% for 100% of the tests in the regression test suite. The pilot project lastedone month ( as planned) and you are currently its results. At the end of the pilot project, 40% of the regression tests have been automated and their execution time has been reduce by 60%.

Which of the following statements is TRUE in this scenario?

Options:

A.

Theduration of the pilot project was too short –it should last unit the success factors are achieved

B.

The target defined for the business case is too accurate –it should not be measureable

C.

The project selected for the pilot is too critical –if should not be too critical or too trivial

D.

The target defined for the business case seems difficult to hit – it should be realistic

Question 3

A SUT has an existing automated test suite.

Which of the following statements relating to the introduction of new features in the SUT is TRUE?

Options:

A.

Automated tests are not affected by the introduction of a new feature and running them against the new SUT is a waste of effort

B.

The introduction of a new feature could require updates or additions to the testware components

C.

The test automation engineer should work with the business analysts to ensure the new feature is testable

D.

It is generally more difficult to automate test cases for a new feature as the developmenthas not yet started