New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium SAP C_TS422_2020 Dumps Questions Answers

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

Options:

A.

Demand Planning (DP)

B.

Material Requirements Planning (MRP)

C.

Capacity Requirements Planning (CRP)

D.

Supply Network Planning (SNP)

Buy Now
Question 2

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? There are 3 correct answers to this question.

Options:

A.

Archiving of documents for assembly scrap

B.

Reduction of associated capacity requirements

C.

Posting of goods receipt for the product

D.

Posting of production costs to the production cost collector

E.

Material staging for next order in sequence

Question 3

In Make-to-order production, which field controls whether the components will be planned as sales order specific stock?

Options:

A.

The item category of the component in the BOM

B.

The MRP Type of the component

C.

The Individual/Collective indicator of the component

D.

The Planning Strategy of the finished product

Question 4

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

Options:

A.

Reduce the planning window.

B.

Adjust the available capacity.

C.

Execute a new production planning run.

D.

Select an alternative mode on a resource.

E.

Form optimum sequences to reduce setup times.

Question 5

What must be used in the system to plan the requirements for different subcontractors separately?

Options:

A.

Planning plant

B.

Storage locations

C.

MRP areas

D.

Production versions

Question 6

You are transferring data from SAP S/4HANAIo embedded PP/OS. What master data objects are mapped to a location? There are 3 correct answers to this question.

Options:

A.

Workcenter

B.

Customer

C.

Plant

D.

Supplier

Question 7

You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question.

Options:

A.

Run setup minimization heuristics or optimizer.

B.

Create and assign setup group/setup keys in the production data structure.

C.

Create and assign a new graphical object for setup time in the planning board.

D.

Create and assign a setup matrix with setup transition time to the resource

Question 8

Where do you maintain the duration of a product on operation?

Options:

A.

Bill of material (BOM)

B.

Work instructions

C.

Material master

D.

Routing

Question 9

How can you set up the supply source for the SAP Kanban process? Note: There are 3 correct answers to this question.

Options:

A.

Using purchase orders for external procurement

B.

Using stock transfer reservations for stock transfer

C.

Using run schedule quantities for in-house production

D.

Using purchasing costs for automated source prioritization

E.

Using quotations for internal and external procurement

Question 10

A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR? There are 2 correct answers to this question.

Options:

A.

Confirmation profile

B.

Scheduling margin key

C.

Operation control key

D.

Production scheduling profile

Question 11

What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

Options:

A.

Stock transport order

B.

Production order

C.

Scheduling agreement schedule line

D.

Purchase requisition

E.

Planned order

Question 12

Which advanced functionality has been embedded in SAP S/4HANA? There are 3 correct answers to this question.

Options:

A.

Available-to-promise

B.

Supply Network Planning

C.

Demand planning

D.

Backorder processing

E.

Capacity planning

Question 13

What does it mean for the production planner when MRP works with infinite capacities?

Options:

A.

MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

B.

MRP creates capacity requirements without checking the capacity of a work center.

C.

MRP creates capacity requirements only if the work center has sufficient capacity.

D.

MRP assigns capacity requirements automatically after the last scheduled order on a work center.

Question 14

You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.

Options:

A.

Checking control must have an overall profile assigned in customizing.

B.

Indicator Relevant for finite scheduling must be set.

C.

Checking rule and group must be assigned.

D.

PRT Availability check must be set.

Question 15

Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

Options:

A.

Change of the material's procurement type

B.

Creation of a purchasing contract

C.

Change of the storage bin

D.

Creation of dependent requirements

E.

Creation of a sales order

Question 16

What are prerequisites for using batch derivation? There are 2 correct answers to this question.

Options:

A.

Batch determination selection conditions

B.

Batch where-used list

C.

Process instructions

D.

Receiver-sender relationships

Question 17

The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings? Please choose the correct answer.

Options:

A.

Plant Settings -> MRP Group —> Material Master

B.

Material Master -> Plant Settings -> MRP Group

C.

Material Master -> MRP Group -> Plant Settings

D.

MRP Group —> Material Master -> Plant Settings

Question 18

You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?

Options:

A.

Top of Red Base

B.

Top of Red

C.

Top of Green

D.

Top of Yellow

Question 19

Where can you find the latest in version of the Simplification List for SAP S/4HANA?

Please choose the correct answer.

Options:

A.

SAP Solution Manager 7.2

B.

SAP Help Portal

C.

SAP Support Portal

D.

SAP Best Practices Explorer

Question 20

A material has been set up as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?

Options:

A.

Change the item category of the phantom assembly in the BOM.

B.

Change the explosion type of the phantom assembly in the BOM.

C.

Change the phantom item indicator for the phantom assembly in the BOM.

D.

Change the special procurement key of the phantom assembly in the BOM.

Question 21

MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

Options:

A.

It is converted into a production order.

B.

It is converted into a reservation.

C.

It is converted into a planned order.

D.

It is converted into a schedule line.

Question 22

Which data object can be updated with the scheduling results of a routing?

Options:

A.

Production scheduling profile

B.

MRP profile

C.

Production version

D.

Material master