Which of the following solutions are feasible when using the time series supply optimizer?Note: There are 3 correct answers to this question.
Which of the following are functions of SAP IBP for demand?Note: There are 2 correct answers to this question.
You are setting up planing with lot sizes.What are some of the properties of lot sizes that you need to be aware of?Note: There are 2 correct answers to this question.
You are working to realign the data due to a recent warehouse closure.What should you be aware of in regards to the realignment steps settings?Note: There are 2 correct answers to this question.
You have set up a planning area, and data is now available. You adjust the necessary time profile settings and run a consistency check.Which settings can you change and still run a successful consistency check?Note: There are 2 correct answers to this question.
You are working on a mid-range plan that spans the seasonal peak and you are evaluating the need for additional crewing.Which of the following parameters can you model to plan production with extra shift(s)?
You have to be logged on to two separate SAP IBP tenants.What can help you differentiate the appearance of their user interfaces?Note: There are 2 correct answers to this question.
Which of the following approaches could you take to reduce run times of an optimizer?Note: There are 3 correct answers to this question.
A time profile is defined with these levels: day, technical week, week, month, quarter, and year. What condition in configuration will allow you to have a different value in the current week, versus all other time buckets?
What are the outputs of the Calculate Target Inventory Components Operator?Note: There are 3 correct answers to this question.
Time profiles are made out of levels, and levels are made out of periods.Which ways can SAP IBP identify profiles and periods?Note: There are 2 correct answers to this question.
You need to create time periods for the time profile in a planning area.What should you be aware of when running the Create Time Periods application job?