VMware vSphere 8.x Advanced Design Questions and Answers

Question 21

An architect is responsible for the lifecycle management design for a brownfield vSphere-based solution.

The following information has been provided during initial meetings around the new solution:

Existing heterogeneous server hardware will be used to provide the hosting platform.

The available hardware is:

- 10 servers that contain 2 x 20-Core Intel Xeon processors and 512 GB RAM from Vendor A

- 10 servers that contain 2 x 24-Core Intel Xeon processors and 768 GB RAM from Vendor A

- 20 servers that contain 2 x 16-Core AMD EPYC processors and 512 GB RAM from Vendor B

- 10 servers that contain 1 x 24-Core AMD EPYC processors and 256 GB RAM from Vendor B

All of the hardware is currently listed on the VMware Hardware Compatibility List (HCL).

All existing server hardware has 36 months vendor support remaining.

The requirements from the customer are:

REQ001 - The solution must support the hosting of 5,000 workloads spread across two physical sites.

REQ002 - The solution should minimize the number of clusters.

REQ003 - The solution must ensure that there is no impact to service when completing upgrades.

Given the resource requirements needed for the solution, the architect has calculated that all of the existing servers will be required to provide sufficient resources for the new environment. The Intel-based (Vendor A) servers will be deployed to the primary site and both the Intel-based and AMD-based servers (Vendor B) will be deployed to the secondary site.

Which assumption should the architect make to support the lifecycle management of vSphere 8?

Options:

A.

The different processor architectures across both sites will remediate against a shared vSphere Lifecycle Manager baseline.

B.

The different processor architectures will be located in the same cluster to support vSphere Lifecycle Manager image-based remediation.

C.

The different processor architecture within a single site will remediate against a single vSphere Lifecycle Manager image.

D.

The different processor architectures across both sites will remediate against a single vSphere Lifecycle Manager image.

Question 22

A company has the requirement to ensure that business-critical applications have the necessary network bandwidth to function optimally and maintain a consistent quality of service (QoS).

Which statement would be included in the conceptual design to support this requirement?

Options:

A.

A distributed switch will be created and Network I/O Control will be enabled.

B.

The network infrastructure must ensure secure communications and efficiently use available bandwidth.

C.

Network resource pool named "bca-pool-02" is given a reservation quota of 5 Gbit/sec.

D.

The distributed switch will use a minimum of 25 Gbps Ethernet.

Question 23

An architect is designing a new vSphere 8 environment and needs to plan the migration of virtual machines from the source vSphere 7 infrastructure.

The following has been captured about the source infrastructure and project:

All virtual machines operate supported versions of Microsoft Windows

All virtual machines have VMware Tools 11 or higher installed

vCenter Enhanced Linked Mode is configured

VMware PowerCLI is available in the environment

No budget is available for discovery tooling

The architect must capture and review active services from inside running virtual machines to inform the migration design.

Considering the information available, which method can the architect use to acquire the information required?

Options:

A.

Request and review the information via VMware vCenter

B.

Deploy and review the service information from VMware Aria Operations

C.

Deploy and review the service information from VMware Aria Operations for Applications

D.

Request and review the information via VMware Tools and VMware PowerCLI

Question 24

An architect is creating the design for a vSphere platform that will be used as the target for a migration from multiple legacy vSphere platforms that are being decommissioned. The customer has provided the following information:

Each legacy platform has its own set of virtual machine templates stored in OVF format.

All of the templates need to be migrated to the new platform.

After migration, the templates should be centralized into a single location.

The templates must be accessible to all clusters in the new platform vCenter instance.

Any new templates added to the central location must be automatically available to all clusters.

Administrators must be able to deploy new virtual machines directly from the template instances.

The customer also confirmed that after the migrations are complete, the new platform will be the only vSphere solution available.

Which design choice should the architect evaluate in the logical design for the storage and management of virtual machine templates?

Options:

A.

Use a dedicated datastore on each vSphere cluster

B.

Use a shared datastore on each vSphere cluster

C.

Use a subscribed content library

D.

Use a local content library