Question 13

In order for Supply and Demand Plans to run successfully, which three Configure Planning Analytic tasks must be completed? (Choose three.)

Options:

A.

Set up Levels and Attributes

B.

Set up Measure Catalogs

C.

Run the Configure Dimension Catalog process

D.

Set up Default Catalogs

E.

Set up Dimension Catalogs

F.

Set up Hierarchy Attributes

Question 14

You are a demand planner and you want to generate forecast for all laptop and desktop products in the US business unit. You are using standard enterprise and product hierarchy. You have created a demand plan and now you must define plan scope.

Identify three valid steps. (Choose three.)

Options:

A.

For plan parameters, select forecasting calendar as Gregorian and time level as week.

B.

For forecasting items, select hierarchy as product, level as category level 1, and laptop and desktop categories as level members.

C.

For plan parameters, select forecasting calendar as Gregorian and time level as month.

D.

For plan organizations, select hierarchy as enterprise, level as country, and US as level member.

E.

For forecasting items, select hierarchy as product, level as product, and all laptop and desktop products as level members.

F.

For plan organizations, select hierarchy as enterprise, level as business unit, and US and level member.

Question 15

During the FIFO pegging process, what is the correct order in which the supplies are sorted?

Options:

A.

Peg demands with reservations first and then peg demands that do not have reservations

B.

Pegging process sorts demands by due dates followed by reservation status

C.

Peg unreserved demands first and then demands with reservations

D.

Pegging process does not respect reservation, and demands are sorted based on demand and supply types

E.

Pegging process does not respect reservation, and demands are sorted based on due dates

Question 16

You analyzed your customer's shipment history data at item and organization level. You found that the customer has many new products with limited history.

Does Planning Central support forecasting products with limited history, and what is this process called?

Options:

A.

No, Planning Central does not support the Croston Method for Sparse Demand forecasting method.

B.

Yes, Planning Central supports the Regression for Sparse Demand forecasting method, typically used for new products.

C.

Yes, Planning Central supports the Holt Exponential Smoothing forecasting method used for newly introduced products.

D.

No, Planning Central does not support the Regression for Sparse Demand forecasting method.

E.

No, Planning Central does not support the Holt Exponential Smoothing forecasting method.