SAFe Agile Product Manager (APM 6.0) Questions and Answers

Question 9

What is one characteristic that is an essential part of market segmentation?

Options:

A.

Exploring competition within the segment

B.

Evaluating if segment members view the organization positively

C.

Validating that the segment is valuable enough to be economically feasible

D.

Determining if the organization already has strong sales within the segment

Question 10

Who commonly facilitates the PO Sync event?

Options:

A.

A Release Train Engineer (RTE)

B.

A Solution Train Engineer (STE)

C.

An Agile Coach

D.

A Scrum Master/Team Coach (SM/TC)

Question 11

The Lean Portfolio Management team is reviewing new work moving through the Portfolio Kanban. Request 1 is incremental innovation and can likely be done by one ART in one PI. Request 2 is a major opportunity impacting multiple stages of the Value Stream, likely requiring the

participation of two ARTs over multiple PIs. Which backlog should each request be added?

Options:

A.

Both should be added to the ART Backlog

B.

Both should be added to the Portfolio Backlog

C.

Request 1 should be added to the Portfolio Backlog as an Epic; Request 2 should be added to the ART Backlog as a Feature

D.

Request 1 should be added to the ART Backlog as a Feature; Request 2 should be added to the Portfolio Backlog as an Epic

Question 12

What metric should Product Managers primarily focus on to help guide the evolution of the products?

Options:

A.

Vanity Metrics

B.

Output Metrics

C.

Outcome Metrics

D.

Flow Metrics