Oracle Project Management Cloud 2022 Implementation Professional Questions and Answers

Question 17

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

Options:

A.

Effort

B.

Cost

C.

Manual Entry

D.

Remaining Plan

Question 18

Your administrator creates maintenance conditions on the Maintain Project Enterprise Labor Resources page. An HCM person is included in a condition with a process order value of 1 and, additionally, there are three other conditions, all with a process order value of 10. Identify two correct statements about the Maintain Project Enterprise Labor Resources process as it relates to process order values. (Choose two.)

Options:

A.

The process creates a resource by using the conditions with a process order value of 10 but does not create more than one resource for the same person even if subsequent conditions apply to the person.

B.

For the three conditions that have the same process order value of 10, the records are processed in ascending alphabetic order based on the condition name.

C.

For the three conditions that have the same process order value of 10, the records are processed in ascending numeric order based on the condition name.

D.

The process creates a resource by using the condition with a process order value of 1 but does not create more than one resource for the same person even if subsequent conditions apply to the person.