Question 13

Fill in the blank with the appropriate term.

______describes the utilization of formal econometric techniques to evaluate the aggregate risk in a financial portfolio

Options:

Question 14

Which of the following is a document that covers the work that will be done, how the work will be compensated, and any penalties for noncompliance?

Options:

A.

Contract

B.

Project description

C.

Cost baseline

D.

Control chart

Question 15

Which of the following processes describes the statement below?

"It consists of the processes required to ensure that the project contains all the work required to complete the project effectively."

Options:

A.

Project communications management

B.

Risk management

C.

Project scope management

D.

Project human resource management

Question 16

In which of the following contract types, the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment which is calculated as a percentage of the initial estimated project costs?

Options:

A.

Communications Management Plan, Execution Process group

B.

Communications Management Plan, Planning Process Group

C.

Project Management Plan, Planning Process Group

D.

Project Management Plan, Initiating Process Group