New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

H12-425_V2.0 Exam Results

HCIP-Data Center Facility Deployment V2.0 Questions and Answers

Question 9

Three UPS5000-E-400Ks from a 2+1 parallel system. Which of the following statements about the parallel system are true?

Options:

A.

The parallel system capacity displayed on the LCD is 1200 kVA.

B.

The networkingmode is set to one-to-multiple for one UPS, and set to one-to-one for the other two UPSs.

C.

If the load is 420 kW, each of two UPSs carries 210 kW load, and the other one is standby and does not carry load.

D.

If the load is 420 kW, each of the three UPSs carries 140kW load.

Question 10

Which of the following menus can be used by engineers to manually add devices on the NetEco?

Options:

A.

Data center planning

B.

Report management

C.

Alarm management

D.

System management

Question 11

Which of the following statements are true about the dry contact card of the integrated UPS?

Options:

A.

After the BCB port of dry contact card is connected, the BCB port can be used only ifit is enabled on the monitoringsoftware.

B.

The EPO port can be normally open or normally closed.

C.

The UPS dry contact card can be used to detect the switch status of the battery system.

D.

The dry contact card cannot detect the status of an external battery switch.

Question 12

To determine whether the R410A refrigerant meets requirements, compare the internal pressure of the refrigerant with the saturation pressure corresponding to the refrigerant temperature. If the difference between the internal pressure and the saturation pressure is within the range of which of the following, replace the refrigerant?

Options:

A.

0-0.05 MPa

B.

0.05-0.1 MPa

C.

0.1-0.2 MPa

D.

0.25-0.3 MPa