Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

GIAC Certification GCPM Dumps PDF

Page: 12 / 15
Total 397 questions

GIAC Certified Project Manager Certification Practice Test Questions and Answers

Question 45

You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Options:

A.

0.87

B.

0.84

C.

0.86

D.

0.80

Question 46

Which of the following models is used to determine, implement, monitor, control, and maintain Information Security Management System or ISMS?

Options:

A.

Continual Service Improvement Model

B.

RACI model

C.

Service Model

D.

PDCA model

Question 47

Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project's performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

Options:

A.

Earned value management method

B.

Time series methods

C.

Causal/econometric methods

D.

Judgmental methods

Question 48

You work as a project manager for PassGuide Inc. You are performing steps to carry out and finish the project according to the measures drawn through the planning stage. Which of the following stages of the project are you working on?

Options:

A.

Monitoring and controlling

B.

Closing

C.

Initiation

D.

Execution

Page: 12 / 15
Total 397 questions