V6 ENOVIA V6 Program Central (V6R2012) Questions and Answers

Question 5

When creating a Route, if Approve is selected in the Action field, the task assignee must:

Options:

A.

choose an approval status only

B.

enter a comment only

C.

mark the task complete only

D.

enter a comment and choose an approval status

Question 6

What metric CANNOT be deleted from Critical to Quality (CTQ)?

Options:

A.

Goal

B.

Controlled

C.

Measured

D.

Predicted

Question 7

In a project with 2 tasks, and no dependencies, the critical path is identified in Red and is the:

Options:

A.

first task

B.

one with the longest time to finish

C.

second task

D.

one with the shortest time to finish

Question 8

When you click on the Program Name link in the search window, you will view a list of all the:

Options:

A.

Projects in that Program

B.

WBS for the Projects

C.

Project members

D.

Projects that are in the Active state