Question 9

You work as a project manager for PassGuide Inc. Your project is in a situation in which a party interested in trading an asset is unable to do so. Which of the following types of risks must have occurred in the above scenario?

Options:

A.

Market risk

B.

Financial risk

C.

Pure risk

D.

Liquidity risk

Question 10

You work as a project manager for PassGuide Inc. You want to calculate the minimum completion time for a project along with the possible start and finish times for the project activities. Which of the following techniques will you use to accomplish the task?

Options:

A.

Time-oriented scheduling

B.

Network scheduling

C.

Critical path scheduling

D.

Resource-oriented scheduling

Question 11

Which of the following statements describes the critical path?

Options:

A.

It is the shortest path in the project network diagram.

B.

It cannot be crashed.

C.

It is always one path with the longest duration.

D.

It shows the project's earliest date for completion.

Question 12

You work as a project manager for PassGuide Inc. You have to achieve authorization for a project and define its objectives. In which of the following stages of a project are you working?

Options:

A.

Planning

B.

Closing

C.

Initiation

D.

Execution