Question 9

According to AVIXA Standards, what is the MINIMUM load rating for truss that will hold a 5000 lbs (2268 kg) LED wall?

Options:

A.

15000 lbs (6804 kg)

B.

25000 lbs (11340 kg)

C.

30000 lbs (13608 kg)

D.

50000 lbs (22678 kg)

Question 10

Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

Options:

A.

circle or oval.

B.

diamond or triangle.

C.

square or rectangle.

D.

asterisk or apostrophe.

Question 11

When designing a projection system for an auditorium, what are the PRIMARY design considerations?

Options:

A.

HVAC layout, rear projection, text height

B.

presenter position, viewing area, aspect ratio

C.

viewing cone, viewing distance, viewing angle

D.

inverse square law, screen gain, reverberation

Question 12

Which of the following project management activities coordinates project requirements and resources?

Options:

A.

project budget

B.

logic model timeline

C.

logic network diagram

D.

project kick-off meeting