New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

AD0-E903 Exam Questions Tutorials

Page: 3 / 5
Total 70 questions

Adobe Workfront Project Manager Professional Questions and Answers

Question 9

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Options:

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Question 10

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

Question 11

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Question 12

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Page: 3 / 5
Total 70 questions