Which is part of quality control?
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
Which is a typical core activity within configuration management?
Which of the following are true statements about a Project Brief?
1. Used to provide a foundation for the Initiating a Project process
2. Created in the Starting up a Project process
3. Used by the Project Board to make an assessment of a project's progress
4. Used as the basis of the Project Initiation Documentation
Who does the Team Manager report to and take direction from?
Which is a purpose of the Directing a Project process?
Which is a true statement about PRINCE2 event-driven controls
Which is a purpose of the Closing a Project process?
Which is a purpose of the Quality theme?
Which is a purpose of the Initiating a Project process?
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
What is an off-specification?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which is an objective of the Directing a Project process?
Which is created during the Starting up a Project process?
Which role is responsible for specifying the project benefits?
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
Identify the missing word(s) in the following sentence.
During a quality review meeting [ ? ] any identified defects.
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
Which role is part of the project management team?
What is the collective name for individuals or groups who may be affected by a project?
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Which is NOT a benefit of using PRINCE2?
Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?
During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
Which is a purpose of the Organization theme?
In what product should the quality criteria for a specialist product be recorded?
Which is a responsibility of a Team Manager?
Which is a task of product-based planning?
Where should a Team Manager look for information on the quality required for a product?
Which is a responsibility of the managing level within the project management team?
What is defined as a temporary organization that is created for the purpose of delivering one or more business products?
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Which is an objective of the Managing Product Delivery process?
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
What is the definition of a project outcome?
Which describes the 'Implement' step within the recommended risk management procedure?
Which is the purpose of the Change theme?
Who should act as the communication channel between a project and corporate or programme
management?