Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Blue Prism ASD01 Dumps Questions Answers

Page: 1 / 2
Total 27 questions

Designing Blue Prism Process Solutions (EN) Questions and Answers

Question 1

Which of the following statements about using Work Queue designs to split a business process into a multi part robotic solution is correct?

1. Using multiple Work Queues and Processes for the different stages of the business process is a valid design option to split a business process into a multi partrobotic solution.

2. Using a single Work Queue and deferring cases for future processing is a valid design option to split a business process into a multi part robotic solution.

3. Using an item’s status to control when to work it is a valid design optionto split a business process into a multi part robotic solution.

4. You cannot split a business process into a multi part robotic solution.

Options:

A.

1 and 2 Only

B.

4 only

C.

1 and 3

D.

1, 2 and 3

Buy Now
Question 2

Consider the following high-level design. Thesolution is intended to read medical data from one application in order to update another. An input file is prepared by an overnight batch run for the solution to work through each morning before patients arrive. Usually the input file is fairly small butat certain times each month the file is much larger.

Which of these options should be considered be the process solution designer to guarantee the quality of the end-to-end solution? (Choose four.)

Options:

A.

Once in production the processcontroller should ensure that the process is only ever run on one Resource PC.

B.

The solution should log in to the applications before starting the case working loop.

C.

The solution should split the file into pieces to distribute to each Resource PC.

D.

The solution should log out from applications after existing working loop.

E.

Each Resource PC should be set to take a different row from the others, e.g. RPC-A works rows 1, 4, 7, 10 etc., RPC-B works 2, 5, 8 etc. and RPC-C works 3, 6, 9 etc.

F.

The solution should start by loading the file data into a work queue.

G.

The file should be updated at the start of each case to prevent other RPCs from working it.

Question 3

Which of the following statement combinations about Blue Prism memory management is correct?

Options:

A.

A Blue Prism Process reads a Business Object into memory as required. Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.A Blue PrismProcess reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

B.

A Blue Prism Process holds a Business Object in memory for the duration of its run.ABlue Prism Process reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

C.

A Blue Prism Process holds a Business Object into memory as required.Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

D.

A Blue Prism Process holds a Sub Process in memory for the duration of its run.A Blue Prism Process holds a Business Object in memory for the duration of its run.

Question 4

Which of the following accurately describes best practice when work is sourced from an application’s workflow system?

Options:

A.

There is no need to use a Blue Prism queue as workflow is managed within the application

B.

Even though there is a workflow system managing and allocating work, a Blue Prism Work Queue should still be used

C.

Blue Prism cannot source work from an application’s workflow system

D.

When sourcing work from an applications workflow system, case data should be stored in an excel document

Question 5

The following Object Design has been created for a mainframe banking application.

Which of the following statements about the Object design above are correct? (Choose two.)

Options:

A.

The Add Note action in the “BankHost – Notepad” business object does not require an input for Type as the process definition document states that ‘Information’ will always be selected for this process.

B.

The object design facilitates a scalable design that will reduce the impact of change when the object layer needs altering.

C.

The object design should be simplified by storing all BankHost actions in the same object.

D.

There is no need for attach actions to be replicated across all the objects.

E.

The design complies with Blue Prism design best practice.

Question 6

If a solution is to make use of a queue with Maximum Attempts greater than 1, what should the designer put in place? (Choose two.)

Options:

A.

Adecision whether or not to use an available retry item after marking an item as an exception.

B.

A decision whether or not to use an available retry item before marking an item complete.

C.

Logic to ensure that the next attempt to work a case is executed on a different machine from the previous attempt.

D.

Logic to ensure that the next attempt to work a case is executed on the same machine as the previous attempt.

E.

Logic to identify the progress made by previous attempts to work a case.

F.

A decision whether or not to use an available retry item after marking an item complete.

G.

A decision whether or not to use an available retry item before marking an item as an exception.

Question 7

Which of the following statements about Blue Prism and Web Services is correct?

Options:

A.

Neither Blue Prism Processes or Business Objects can be exposed as a Web Service

B.

Only Blue Prism Processes can beexposed as a Web Service

C.

Only Blue Prism Business Objects can be exposed as a Web Service

D.

Both Blue Prism Processes or Business Objects can be exposed as a Web Service

Question 8

Consider the following steps for a theoretical manual process.

  • Check in input folder any newfiles.
  • If there are no files check again later as files can arrive anytime, and there is no limit to the number of files that may come.
  • Open the next available file.
  • Take the first case.
  • Start System X and find the case details.
  • If the case can’t be found, move to the next one.
  • After finding the case in System X, fetch additional case details from System Y.
  • Again if the case can’t be found, move to the next one.
  • Analyse all the data to see if System Z should be updated.
  • If the data does not meet the requirements, add notes indicating this to System X and Y and move to the next case.
  • If the data does meet the requirements, update the case in System Z.
  • Add notes to System X and Y and move to the next case.
  • At the end of the file, go back andlook for another.
  • Stop checking for new files at 16:00 and finish any remaining cases.
  • When all work is complete create a report of the day’s exception cases.
  • Close down Systems X, Y and Z.

If the volume of incoming cases is such that 1 Resource PC can easily handle the workload, which of the following steps for an automated solution should be part of the ‘Preparation’ phase of an automated process?

Options:

A.

Check input folder, wait for files.

B.

Check input folder, wait for files, read file and load queue.

C.

Log into applications.

D.

Check input folder, wait for files, read file and load queue, log into applications.

Exam Detail
Vendor: Blue Prism
Certification: Solution Designer
Exam Code: ASD01
Last Update: Nov 23, 2024
ASD01 Question Answers
Page: 1 / 2
Total 27 questions