New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

AACE International CCP Based on Real Exam Environment

Page: 11 / 14
Total 189 questions

Certified Cost Professional (CCP) Exam Questions and Answers

Question 41

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

Options:

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Question 42

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The recognition of loss of value of a natural resource used in the production process is referred to as:

Options:

A.

Capital reduction

B.

Net loss

C.

Depreciation

D.

Depletion

Question 43

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:

A.

$60,000

B.

$41,250

C.

$33,000

Question 44

You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:

unable to be calculated from the information given

Options:

A.

<1

B.

=1

C.

=1

D.

>1

Page: 11 / 14
Total 189 questions