Question 57

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Question 58

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

Options:

A.

1

B.

2

C.

3

D.

4

Question 59

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

Options:

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Question 60

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

Options:

A.

Meet with the stakeholder and discuss timeline impact.

B.

Refer changes to the project manager.

C.

Define requirements baseline and implement a change control process.

D.

Implement only the original requirements.