New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CPIM CPIM-ECO Full Course Free

Page: 2 / 4
Total 105 questions

Execution and Control of Operations Questions and Answers

Question 5

A work center has a balance between the scheduled input and output over the next 4 weeks. One of the three machines in the work center will be out of service for 1 week. Currently, three operators work the first shift, one operator works the second shift, and each has a 40-hour work week. Which of the following actions is best to take to maintain the schedule?

Options:

A.

Move an operator from the first to the second shift.

B.

Schedule 40 hours of overtime.

C.

Subcontract 40 hours of work.

D.

Adjust the input.

Question 6

A company is gathering data as to why the machine is consistently shutting down. What methodology should a company pursue first?

Options:

A.

5S

B.

Plan-do-check-act

C.

Kaizen event

D.

Statistical process control

Question 7

Proper workplace organization calls for which of the following actions?

Options:

A.

Increasing supervisor oversight

B.

Returning frequently used items to a nearby, fixed location

C.

Increasing the use of kanbans

D.

Placing all tools in a centrally located tool crib

Question 8

Which of the following components are associated with inventory functions?

Options:

A.

Transit, cycle, and warehousing

B.

Transit, cycle, and safety stock

C.

Safety stock, anticipation, and work in process (WIP)

D.

Raw, work in process (WIP), and finished goods

Page: 2 / 4
Total 105 questions