Question 5

Company ABC always works in the following way: The business chooses a set of requirements that it believes will add business value. It communicates the requirements to the IT organization. The IT organization responds back with a plan and estimates of cost and schedule. The business agrees to that plan. The IT organization executes the plan and delivers a product to the business.

What type of framework is company ABC following?

Options:

A.

DevOps

B.

DSDM

C.

Lean

D.

Waterfall

Question 6

A Product Owner is refining the product backlog She has provided more details to stones that nave a higher priority after speaking with several customers She has also grouped several user stories with a lower priority into epics

Is this the right way to refine the product backlog?

Options:

A.

Yes because customer requirements that are very clear lead to detailed stories

B.

Yes because stories with high priority should be pulled into a sprint backlog soon

C.

No. because any story in the product backlog can be either detailed or coarse-grained

D.

No. because grouping the user stories into epics leads to losing important details

Question 7

A new Sprint has just started in your project. Some of the Development Team members need help determining when team members will actually take ownership of a Sprint Backlog item. What should you tell the Development Team?

Options:

A.

Sprint Backlog items are owned by the entire Development Team, not individuals.

B.

Ownership happens once the Scrum Master assigns a task to a Development Team member.

C.

The team should slice the Sprint Backlog into assignments as soon as the Sprint begins.

D.

The Development Team should elect a team leader that will assign tasks to the other Development Team members.

Question 8

All of the following statements about Risk Communications are true, EXCEPT:

Options:

A.

The Stakeholders should be continuously informed about risks, including the potential impact of these risks

and the plans for responding to each risk.

B.

The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during

Daily Standup Meetings.

C.

The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to

the Scrum Team.

D.

Information related to risks is maintained and updated through the Risk Burndown Chart.